Custom Solution: Remote PIG Retrieval

Overview

A Middle Eastern client approached AISUS with an urgent operational challenge on a Well Head Platform in Qatar. A PIG had become lodged approximately 7 metres beyond the PIG launcher, within the first isolation value of a 38″ wet gas line, leaving no established method for safe retrieval. Recognising the critical nature of the issue, AISUS rapidly mobilised engineering resources to assess the challenge and develop a safe, practical and fully engineered retrieval solution. Within 10 days of the issue being reported. AISUS had designed, fabricated and tested a bespoke remote PIG retrieval tool, together with a detailed deployment methodology, ready for execution.

 

Requirement

The client required a safe means of retrieving the stuck PIG without personnel entry into the launcher. The solution needed to be operated remotely over a distance of approximately 7 metres while generating sufficient force recover the obstruction. Given the operational impact and the critical nature of the pipework, the solution also needed to be designed, approved and ready for deployment within an exceptionally short timeframe.

Challenges

The project presented a unique engineering challenge. The PIG was located within the first isolation valve in critical live pipework with only a single isolation in place, creating significant constraints around intervention methods. No existing tooling was available that could safely complete the task, requiring a completely bespoke approach. The retrieval system also needed to deliver up to 14 tonnes of pulling force while maintaining safe remote operation.

Solution

AISUS responded immediately, working closely with the client to develop a fit-for-purpose retrieval system tailored to the operational conditions. A brand-new remote PIG retrieval tool was designed, engineered and fabricated in-country specifically for the scope, significantly reducing lead times and enabling rapid deployment readiness.

To support client review and approval, AISUS supplied detailed 3D models and animations, allowing the proposed methodology to be visualised and assessed before mobilisation. The completed system underwent onshore testing to verify performance and ensure operational readiness, while a comprehensive scope of work and deployment plan were prepared to support execution.

By combining engineering expertise from Aberdeen with established Middle East operations and personnel, AISUS  was able to transform an urgent client challenge into fully engineered, tested and deployment-ready solution in just 10 days.

 

Benefits to Client

The project demonstrated AISUS’s ability to respond rapidly to complex operational challenges, developing bespoke technology where no conventional solution existed. Through local fabrication, detailed engineering validation and clear visualisation of the proposed methodology, the client was provided with a safe practical and technical robust retrieval solution within an accelerated timeframe.

Client Testimonial

“AISUS’s regional technical lead Andy, was extremely responsive, professional and a brilliant problem solver throughout the project”

 

Contact Us to find out more → https://www.aisus.co.uk/contact/ 

Recent Case Studies

Project c|Ai|sson: Predicting Future Caisson Integrity Through AI-Driven Forecasting

Overview For more than a decade, AISUS has deployed remote robotic inspection technologies across offshore assets worldwide, providing operators with safe and cost-effective access to critical infrastructure. Through thousands of inspections, AISUS has built an extensive dataset on the condition and degradation of offshore caissons, many of which continue to operate beyond their original design […]

Internal cleaning & UT Inspection of North Sea Conductors

Overview AISUS were commissioned by a North Sea operator to undertake a comprehensive internal cleaning and inspection campaign on ten conductors ranging from 20″ to 30″ in diameter. The work formed a critical part of a large-scale decommissioning project and was completed in advance of a planned cut-and-pin operation. The primary objective was to provide […]

Bespoke Clamshell Tool for External Riser Inspection

Overview AISUS was engaged by a North Sea offshore operator to undertake external cleaning and Pulsed Eddy Current Testing (PECT) inspection of two 6″ OD risers through the splash zone. The project presented several challenges, including restricted access, the presence of heavy marine growth and 50 mm thick passive fire protection (PFP) coating. To overcome […]
ENQUIRE NOW